← All districts

Baghpat, Uttar Pradesh

Not a Scheduled AreaCensus 2011 district code 139

No proposal naming this district recorded a step between 30 Aug 2026 and 28 Oct 2026.

Dated by the portal's own appraisal history, converted to India Standard Time; a proposal with no recorded history appears on its register submission date.

Other clearances these proposals declare

Forest land diversion declared
1
Forest land sought for diversion
Area not stated
Wildlife board recommendation declared
1
In or near a protected area
0
In an eco-sensitive zone
1

These counts are taken from the application forms of the 27 of 27 proposals naming this district whose forms have been read for these questions. In 14 of those forms at least one question was left blank, and a blank answer is counted as unknown. The forest area is the area stated for forest clearance, with each forest proposal counted once, in the district where its project is primarily sited.

Proposals naming this district
27
Category A proposals
3
Families declared displaced
None declared
Families declared affected
None declared

Displacement figures are the proponents’ own declarations. A project sited across several districts declares one figure for the whole project, and that figure is counted once, in the district where the project is primarily sited.

Fifth Schedule status

Not within a Fifth Schedule Scheduled Area

No Presidential Order under paragraph 6 of the Fifth Schedule declares any Scheduled Area in Uttar Pradesh, so no part of this district is one and PESA does not apply.

OrderMinistry of Tribal Affairs, Scheduled Areas declared under paragraph 6 of the Fifth Schedule to the Constitution

Who lives there

Figures from Census 2011, each compared with the all-India value computed on the same definition.

Total population
13,03,048
Households
2,09,916
Average household size
6.21
1.36 above India's 4.85India
Scheduled Tribe share of population
0.0%
8.6 points below IndiaIndia
Scheduled Caste share of population
11.4%
5.2 points below IndiaIndia
Children aged 0-6
15.0%
1.4 points above IndiaIndia
Literacy rate
72.0%
1.0 points below IndiaIndia
Sex ratio
861
81.3 below India's 942.6India

What they live on

How the district's workers earn a living, from Census 2011. The land-dependent share counts cultivators and agricultural labourers as a share of all workers, and it is the group most directly affected when land is acquired.

Total workers
4,16,695
Work participation rate
32.0%
7.8 points below IndiaIndia
Workers dependent on land
47.8%
6.8 points below IndiaIndia
Cultivators
29.9%
5.3 points above IndiaIndia
Agricultural labourers
17.9%
12.0 points below IndiaIndia
Marginal workers
19.7%
5.0 points below IndiaIndia
Household industry workers
4.9%
1.1 points above IndiaIndia

How households live

Land, income and work among rural households, from the Socio Economic and Caste Census 2011, which recorded these where the population census did not. Only the survey's rural part is used here, so urban households do not appear.

Rural households owning land
35.4%
10.7 points below IndiaIndia

The India figure is computed from 614 of 640 districts, because the source table has no value for the others.

Rural households whose highest earner makes over ₹5,000 a month
58.9%
34.6 points above IndiaIndia

The India figure is computed from 614 of 640 districts, because the source table has no value for the others.

Rural households living mainly on manual casual labour
34.4%
17.4 points below IndiaIndia

The India figure is computed from 614 of 640 districts, because the source table has no value for the others.

Rural households with a salaried member
12.2%
3.9 points above IndiaIndia

The India figure is computed from 614 of 640 districts, because the source table has no value for the others.

When these were filed

Each proposal is dated by the first step in its appraisal history, the dated record of steps the portal keeps for it.

2023-Q22026-Q2

The timeline counts 21 of the 27 proposals here. The first filing date comes from each proposal's appraisal history, and we have not yet read it for the other 6, so they are left out. Most of them are older proposals, so the early part of the timeline undercounts what was filed then. The register itself records a date for each of them; the gap is in our copy of the histories.

Hatched columns undercount, so they cannot be compared with solid ones. One of them covers a period for which we have read few filing dates so far, and it counts only the proposals whose date we have.

What kind of projects these are

The proposals naming this district, grouped by the sector each was filed under.

  • Non-Coal Mining 74.1%
  • Industrial Projects - 2 11.1%
  • INFRA-2 7.4%
  • Industrial Projects - 3 7.4%

The four largest sectors are shown by name and the rest are grouped as Other.

What is proposed here

These are the proposals in the national environmental clearance register whose application names a site in this district, newest first. A project with sites in several districts appears under each of them.

  1. Category AForwarded to MS SPCB/PCC by MS2026-06-15

    Laying of LPG pipeline from Chirai Nani village to Par village (18.908 km in multiple patches) and Kotda village to Nichlo Bandh village (6.508 km in multiple patches) as part of capacity expansion of Jamnagar-Loni pipeline project, 1099.44 Km Pipeline from 3.25 to 6.5 MMTPA by M/s GAIL (India) Limited

    GAIL INDIA LIMITED · Industrial Projects - 2

  2. Category B1EC Granted2026-04-17

    Proposed Sand mining (Minor Mineral) from the Riverbed of Yamuna with 20,17,000 TPA production over an area of 51.15 Ha located at Village Bega, Tehsil-Ganaur, District – Sonipat, State- Haryana by M/s Tirupati Earth & Project Work Pvt. Ltd

    TIRUPATI EARTH AND PROJECT WORKS PRIVATE LIMITED · Non-Coal Mining

  3. Category B2EC Granted2025-12-16

    Factory Building Project located at Village- Duala, Meerut-Baghpat Road, Tehsil & District-Baghpat, Uttar Pradesh by M/s Bimbo Bakeries India Private Limited

    bimbo bakeries india private limited · INFRA-2

  4. Category B2EC Granted2025-12-10

    Ranchad Soil Mining Project

    MURTAJA · Non-Coal Mining

  5. Category B2EC Granted2025-12-03

    Pawla Begamabad Soil Mining Project

    SUDHIR SHARMA · Non-Coal Mining

  6. Category B2EC Granted2025-12-03

    Gauripur Jawaharnagar Soil Mining Project

    SUDHIR SHARMA · Non-Coal Mining

  7. Category B1EC Granted2025-10-14

    “Ordinary Sand Mining” from Riverbed of Yamuna River at Village-Gauripur Khadar, Gata No.- 3, 4 & 5क, Lease Area- 14.0224 ha. Tehsil– Baghpat District– Baghpat, Uttar Pradesh, Project Proponent- Manish Jaiswal/99092 (Contact Person- Shri Manish Jaiswal)

    MANISH JAISWAL · Non-Coal Mining

  8. Category B1EC Granted2025-10-08

    “Ordinary Sand Mining” from Riverbed of Yamuna River at Village- Badarkha Khadar, Gata No.- 1/2/1, Lease Area- 17.460 Ha., Tehsil– Baraut District– Baghpat, Uttar Pradesh, Project Proponent- M/s Aravalli Mines and Minerals/547853(Contact person- Smt Janki Devi)

    janki devi · Non-Coal Mining

  9. Category B2EC Granted2025-09-27

    Khekda Pratham Soil Mining Project

    SUDHIR SHARMA · Non-Coal Mining

  10. Category B2Proposal pulled back (withdrawn)2025-09-08

    Khekda Pratham Soil Mining Project

    SUDHIR SHARMA · Non-Coal Mining

  11. Category B2EC Granted2025-08-18

    Banas Dairy (Amul)

    BANASKANTHA DIST CO OP MILK PRODUCERS UNION LTD · INFRA-2

  12. Category B1EC Granted2025-04-25

    NAITHALA KHADAR SAND MINING PROJECT

    RAJIV SINGH · Non-Coal Mining

  13. Category B1ToR Granted2025-04-11

    “Ordinary Sand Mining” from Riverbed of Yamuna River at Village-Gauripur Khadar, Gata No.- 3, 4 & 5क, Lease Area- 14.0224 ha. Tehsil– Baghpat District– Baghpat, Uttar Pradesh, Project Proponent- Manish Jaiswal/99092 (Contact Person- Shri Manish Jaiswal)

    MANISH JAISWAL · Non-Coal Mining

  14. Category B1ToR Granted2025-02-06

    “Ordinary Sand Mining” from Riverbed of Yamuna River at Village- Badarkha Khadar, Gata No.- 1/2/1, Lease Area- 17.460 Ha., Tehsil– Baraut District– Baghpat, Uttar Pradesh, Project Proponent- M/s Aravalli Mines and Minerals/547853(Contact person- Smt Janki Devi)

    janki devi · Non-Coal Mining

  15. Category B1ToR Granted2024-09-14

    NAITHALA KHADAR SAND MINING PROJECT

    RAJIV SINGH · Non-Coal Mining

  16. Category B2EC Granted2024-07-30

    BAGHU SOIL MINING PROJECT

    SHER SINGH · Non-Coal Mining

  17. Category B1EC Granted2024-07-23

    Proposed expansion of existing Sugar unit from 8000 TCD to 10000 TCD along with Co gen power plant - 36 MW within existing premises at Village- Loyan Malakpur, Block & Tehsil – Baraut, District- Baghpat (U.P.) by M/s SBEC Sugar Limited

    SBEC SUGAR LIMITED · Industrial Projects - 2

  18. Category B1ToR Granted2024-04-25

    Proposed Sand mining (Minor Mineral) from the Riverbed of Yamuna with 20,17,000 TPA production over an area of 51.15 Ha located at Village Bega, Tehsil-Ganaur, District – Sonipat, State- Haryana by M/s Tirupati Earth & Project Work Pvt. Ltd

    TIRUPATI EARTH AND PROJECT WORKS PRIVATE LIMITED · Non-Coal Mining

  19. Category B1Standard ToR Granted2024-01-30

    Proposed expansion of existing Sugar unit from 8000 TCD to 10000 TCD along with Co gen power plant - 36 MW within existing premises at Village- Loyan Malakpur, Block & Tehsil – Baraut, District- Baghpat (U.P.) by M/s SBEC Sugar Limited

    SBEC SUGAR LIMITED · Industrial Projects - 2

  20. Category AEC Granted2023-11-17

    Proposed manufacturing unit of Formaldehyde (100 TPD), Urea Formaldehyde Thermosetting Moulding Powder (5 TPD) and Melamine Formaldehyde Thermosetting Moulding Powder (6.6 TPD) at Plot No. B-47 to B-49 at UPSIDA Industrial Area, Baghpat Tehsil- Baghpat, District- Baghpat, Uttar Pradesh by White Field Chemicals

    M/S WHITE FIELD CHEMICALS · Industrial Projects - 3

  21. Category B1EC Granted2023-08-27

    “Ordinary Sand Mining” Project at Gata No.- 620, 634, Village- Sankraudh Khadar, Tehsil- Khekda, District- Baghpat, U.P. (Leased Area : 7.0 ha.)

    SMART MART STORES PRIVATE LIMITED · Non-Coal Mining

  22. Category B1EC Granted2023-08-24

    Kotana Khadar Ordinary Sand Mining on Yamuna Riverbed Project

    DAYACHAND BADGOTI · Non-Coal Mining

  23. Category B1EC Granted2023-08-10

    Proposed Chhaprauli Khadar Ordinary Sand Mining project on Yamuna Riverbed

    DAYACHAND BADGOTI · Non-Coal Mining

  24. Category AStandard ToR Granted2023-06-16

    Proposed manufacturing unit of Formaldehyde (100 TPD), Urea Formaldehyde Thermosetting Moulding Powder (5 TPD) and Melamine Formaldehyde Thermosetting Moulding Powder (6.6 TPD) at Plot No. B-47 to B-49 at UPSIDA Industrial Area, Baghpat Tehsil- Baghpat, District- Baghpat, Uttar Pradesh by White Field Chemicals

    M/S WHITE FIELD CHEMICALS · Industrial Projects - 3

  25. Category B1TOR Granted2023-03-09

    Ordinary Sand Mining” on the riverbed of Yamuna River

    DAYACHAND BADGOTI · Non-Coal Mining

  26. Category B1TOR Granted2023-03-06

    “Ordinary Sand Mining” Project at Gata No.- 620, 634, Village- Sankraudh Khadar, Tehsil- Khekda, District- Baghpat, U.P. (Leased Area : 7.0 ha.)

    SMART MART STORES PRIVATE LIMITED · Non-Coal Mining

  27. Category B1TOR Granted2023-02-10

    Proposed Chhaprauli Khadar Ordinary Sand Mining project on Yamuna Riverbed

    DAYACHAND BADGOTI · Non-Coal Mining

All 27 proposals that name this district, newest first.