← All districts

Sultanpur, Uttar Pradesh

Not a Scheduled AreaCensus 2011 district code 179
  1. 20 Oct 2026 · DecidedStandard Terms of Reference grantedProposed Brownfield Urea Expansion Project having a capacity of 2500 TPD Ammonia Plant and 4500 TPD Urea…
  2. 19 Oct 2026 · FiledSubmittedProposed Brownfield Urea Expansion Project having a capacity of 2500 TPD Ammonia Plant and 4500 TPD Urea…
  3. 15 Oct 2026 · DecidedGrantedTransfer of Environmental clearance from Indo-Gulf Fertilizers Limited (a unit of Grasim Industries…
  4. 24 Sept 2026 · Details soughtAdditional details soughtTransfer of Environmental clearance from Indo-Gulf Fertilizers Limited (a unit of Grasim Industries…
  5. 31 Aug 2026 · Details soughtAdditional details soughtTransfer of Environmental clearance from Indo-Gulf Fertilizers Limited (a unit of Grasim Industries…

Dated by the portal's own appraisal history, converted to India Standard Time; a proposal with no recorded history appears on its register submission date.

Other clearances these proposals declare

Forest land diversion declared
0
Forest land sought for diversion
None declared
Wildlife board recommendation declared
0
In or near a protected area
0
In an eco-sensitive zone
0

These counts are taken from the application forms of the 11 of 11 proposals naming this district whose forms have been read for these questions. In 3 of those forms at least one question was left blank, and a blank answer is counted as unknown. The forest area is the area stated for forest clearance, with each forest proposal counted once, in the district where its project is primarily sited.

Proposals naming this district
11
Category A proposals
3
Families declared displaced
None declared
Families declared affected
None declared

Displacement figures are the proponents’ own declarations. A project sited across several districts declares one figure for the whole project, and that figure is counted once, in the district where the project is primarily sited.

Fifth Schedule status

Not within a Fifth Schedule Scheduled Area

No Presidential Order under paragraph 6 of the Fifth Schedule declares any Scheduled Area in Uttar Pradesh, so no part of this district is one and PESA does not apply.

OrderMinistry of Tribal Affairs, Scheduled Areas declared under paragraph 6 of the Fifth Schedule to the Constitution

What the record shows

  • Agricultural labourers, who work other people's land for wages, make up 40% of workers here. Compensation for acquired land is paid to those who hold title to it, so it does not reach them. They can still claim the rehabilitation and resettlement entitlements of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (RFCTLARR), because its section 3(c) counts a family whose livelihood depends on the land as an affected family, wherever that Act governs how the land is obtained.

Each of these observations appears when a fixed rule is met by the figures on this page, so the same figures always give the same sentences. None of them is a view on whether a project should go ahead.

Who lives there

Figures from Census 2011, each compared with the all-India value computed on the same definition.

Total population
37,97,117
Households
6,23,523
Average household size
6.09
1.24 above India's 4.85India
Scheduled Tribe share of population
0.0%
8.5 points below IndiaIndia
Scheduled Caste share of population
22.4%
5.8 points above IndiaIndia
Children aged 0-6
14.8%
1.3 points above IndiaIndia
Literacy rate
69.3%
3.7 points below IndiaIndia
Sex ratio
983
40.7 above India's 942.6India

What they live on

How the district's workers earn a living, from Census 2011. The land-dependent share counts cultivators and agricultural labourers as a share of all workers, and it is the group most directly affected when land is acquired.

Total workers
12,42,632
Work participation rate
32.7%
7.1 points below IndiaIndia
Workers dependent on land
67.6%
13.1 points above IndiaIndia
Cultivators
27.3%
2.6 points above IndiaIndia
Agricultural labourers
40.4%
10.4 points above IndiaIndia
Marginal workers
44.4%
19.7 points above IndiaIndia
Household industry workers
6.9%
3.1 points above IndiaIndia

How households live

Land, income and work among rural households, from the Socio Economic and Caste Census 2011, which recorded these where the population census did not. Only the survey's rural part is used here, so urban households do not appear.

Rural households owning land
57.6%
11.5 points above IndiaIndia

The India figure is computed from 614 of 640 districts, because the source table has no value for the others.

Rural households whose highest earner makes over ₹5,000 a month
33.4%
9.0 points above IndiaIndia

The India figure is computed from 614 of 640 districts, because the source table has no value for the others.

Rural households living mainly on manual casual labour
48.6%
3.2 points below IndiaIndia

The India figure is computed from 614 of 640 districts, because the source table has no value for the others.

Rural households with a salaried member
10.7%
2.4 points above IndiaIndia

The India figure is computed from 614 of 640 districts, because the source table has no value for the others.

When these were filed

Each proposal is dated by the first step in its appraisal history, the dated record of steps the portal keeps for it.

2024-Q42026-Q4

The timeline counts 6 of the 11 proposals here. The first filing date comes from each proposal's appraisal history, and we have not yet read it for the other 5, so they are left out. Most of them are older proposals, so the early part of the timeline undercounts what was filed then. The register itself records a date for each of them; the gap is in our copy of the histories.

Hatched columns undercount, so they cannot be compared with solid ones. 2026-Q4 was still running when the register was read, so its column counts only the filings made up to that date.

What kind of projects these are

The proposals naming this district, grouped by the sector each was filed under.

  • INFRA-2 36.4%
  • Industrial Projects - 3 27.3%
  • INFRA-1 18.2%
  • Industrial Projects - 2 18.2%

The four largest sectors are shown by name and the rest are grouped as Other.

What is proposed here

These are the proposals in the national environmental clearance register whose application names a site in this district, newest first. A project with sites in several districts appears under each of them.

  1. Category AForwarded to MS SPCB/PCC by MS2026-10-19

    Proposed Brownfield Urea Expansion Project having a capacity of 2500 TPD Ammonia Plant and 4500 TPD Urea Plant, along with related offsite, utility & auxiliary facilities by M/s Indorama India Private Limited (IIPL)

    INDORAMA INDIA PRIVATE LIMITED · Industrial Projects - 3

  2. Category AGranted2026-08-05

    Transfer of Environmental clearance from Indo-Gulf Fertilizers Limited (a unit of Grasim Industries Limited) to Indorama India Private Limited

    INDORAMA INDIA PRIVATE LIMITED · Industrial Projects - 3

  3. Category AProposal returned in present form2025-12-05

    Transfer of Environmental clearance from Indo-Gulf Fertilizers Limited (a unit of Grasim Industries Limited) to Indorama India Private Limited

    INDORAMA INDIA PRIVATE LIMITED · Industrial Projects - 3

  4. Category B1Forwarded to MS SPCB/PCC by MS2025-10-18

    Proposed Integrated Manufacturing & Logistic Cluster (IMLC) Amethi at Villages - Sewara, Husenpur, Sindhiyawan and Unchgaun Tehsil - Musafirkhana va Haidargarh, District - Amethi, State - Uttar Pradesh by Uttar Pradesh Expressways Industrial Development Authority (UPEIDA).

    UTTAR PRADESH EXPRESSWAYS INDUSTRIAL DEVELOPMENT AUTHORITY (UPEIDA) · INFRA-1

  5. Category B1ToR Granted2025-10-10

    Proposed Integrated Manufacturing & Logistic Cluster (IMLC) Sultanpur at Villages - Kareban, Mahmudpur Semri, Lathawa, Kalyanpur, Vishundaspur, Chandpur, Chiranedih, Savai, Amaliya Shikara and Semri, Tehsil - Jaysinghpur, District - Sultanpur, State - Uttar Pradesh by Uttar Pradesh Expressways Industrial Development Authority (UPEIDA).

    UTTAR PRADESH EXPRESSWAYS INDUSTRIAL DEVELOPMENT AUTHORITY (UPEIDA) · INFRA-1

  6. Category B2EC Granted2024-12-03

    Construction of 17 Nos. Court and other allied buildings for Integrated Court Complex at District – Amethi, Uttar Pradesh.

    ASHOK KUMAR SINGH · INFRA-2

  7. Category B1EC Granted2023-11-30

    ESTABLISHMENT OF PROPOSED GRAIN BASED DISTILLERY CAPACITY – 60 KLD ALONG WITH CO GEN POWER OF 2.0 MW AT VILLAGE: GOPALPUR DUBEY, TEHSIL: KADIPUR, DISTRICT: SULTANPUR, UTTAR PRADESH BY M/S GLYCO ARUNA PRIVATE LIMITED

    GLYCO ARUNA PRIVATE LIMITED · Industrial Projects - 2

  8. Category B2EC Granted2023-10-06

    Construction of residential and non-residential buildings of police line Amethi

    SUPERINTENDENT OF POLICE AMETHI · INFRA-2

  9. Category B2EDS Raised2023-08-08

    CONSTRUCTION OF RESIDENTIAL AND NON RESIDENTIAL BUILDINGS OF POLICE LINE AMETHI

    ANAND SHARMA · INFRA-2

  10. Category B1TOR GRANTED2023-04-15

    ESTABLISHMENT OF PROPOSED GRAIN BASED DISTILLERY CAPACITY – 60 KLD ALONG WITH CO GEN POWER OF 2.0 MW AT VILLAGE: GOPALPUR DUBEY, TEHSIL: KADIPUR, DISTRICT: SULTANPUR, UTTAR PRADESH BY M/S GLYCO ARUNA PRIVATE LIMITED

    GLYCO ARUNA PRIVATE LIMITED · Industrial Projects - 2

  11. Category B2EC Granted2023-03-15

    Proposed District Jail complex (990 capacity) at Amethi, Uttar Pradesh

    PREM SINGH · INFRA-2

All 11 proposals that name this district, newest first.