  1. 28 Sept 2026 · FiledSubmittedKurung Hydro Electric Project (292 MW)

Dated by the portal's own appraisal history, converted to India Standard Time; a proposal with no recorded history appears on its register submission date.

Other clearances these proposals declare

Forest land diversion declared
3
Forest land sought for diversion
471 ha
Wildlife board recommendation declared
0
In or near a protected area
0
In an eco-sensitive zone
0

These counts are taken from the application forms of the 7 of 7 proposals naming this district whose forms have been read for these questions. In 4 of those forms at least one question was left blank, and a blank answer is counted as unknown. The forest area is the area stated for forest clearance, with each forest proposal counted once, in the district where its project is primarily sited.

Proposals naming this district
7
Category A proposals
7
Families declared displaced
191
Families declared affected
881

Displacement figures are the proponents’ own declarations. A project sited across several districts declares one figure for the whole project, and that figure is counted once, in the district where the project is primarily sited. 4 of the proposals listed below declare displacement and are sited primarily in another district, so their figures are counted in that district’s total.

Fifth Schedule status

Not within a Fifth Schedule Scheduled Area

No Presidential Order under paragraph 6 of the Fifth Schedule declares any Scheduled Area in Arunanchal Pradesh, so no part of this district is one and PESA does not apply. A different protection does apply here: the Bengal Eastern Frontier Regulation 1873 (Inner Line) and State land law; the Fifth Schedule has never been extended to it.

OrderMinistry of Tribal Affairs, Scheduled Areas declared under paragraph 6 of the Fifth Schedule to the Constitution

What the record shows

  • Half or more of the people counted here in 2011 were Scheduled Tribe: 98.6%, against 8.55% nationally.

  • Cultivators and agricultural labourers make up 80% of workers here, against 55% nationally, so at least three in four people who work here do so on the land.

  • Literacy was 48.8% in 2011 against 72.98% nationally, so notices and documents issued in writing during a consultation may reach fewer people here.

  • 7 clearance proposals name this district, where 99% of people are Scheduled Tribe and 80% of workers depend on the land. 7 of those proposals are Category A, the class the central government appraises.

  • Applicants for projects sited mainly in this district have declared 191 families to be displaced. The figure comes from their applications, and we have not verified it.

Each of these observations appears when a fixed rule is met by the figures on this page, so the same figures always give the same sentences. None of them is a view on whether a project should go ahead.

Who lives there

Figures from Census 2011, each compared with the all-India value computed on the same definition.

Total population
92,076
Households
15,037
Average household size
6.12
1.27 above India's 4.85India
Scheduled Tribe share of population
98.6%
90.0 points above IndiaIndia
Scheduled Caste share of population
0.0%
16.6 points below IndiaIndia
Children aged 0-6
18.5%
4.9 points above IndiaIndia
Literacy rate
48.8%
24.2 points below IndiaIndia
Sex ratio
1,032
89.2 above India's 942.6India

What they live on

How the district's workers earn a living, from Census 2011. The land-dependent share counts cultivators and agricultural labourers as a share of all workers, and it is the group most directly affected when land is acquired.

Total workers
38,044
Work participation rate
41.3%
1.5 points above IndiaIndia
Workers dependent on land
79.8%
25.3 points above IndiaIndia
Cultivators
72.1%
47.4 points above IndiaIndia
Agricultural labourers
7.8%
22.2 points below IndiaIndia
Marginal workers
35.9%
11.2 points above IndiaIndia
Household industry workers
2.2%
1.6 points below IndiaIndia

How households live

Land, income and work among rural households, from the Socio Economic and Caste Census 2011, which recorded these where the population census did not. Only the survey's rural part is used here, so urban households do not appear.

Rural households owning land
54.6%
8.5 points above IndiaIndia

The India figure is computed from 614 of 640 districts, because the source table has no value for the others.

Rural households whose highest earner makes over ₹5,000 a month
23.9%
0.4 points below IndiaIndia

The India figure is computed from 614 of 640 districts, because the source table has no value for the others.

Rural households living mainly on manual casual labour
7.1%
44.7 points below IndiaIndia

The India figure is computed from 614 of 640 districts, because the source table has no value for the others.

Rural households with a salaried member
7.6%
0.7 points below IndiaIndia

The India figure is computed from 614 of 640 districts, because the source table has no value for the others.

When these were filed

Each proposal is dated by the first step in its appraisal history, the dated record of steps the portal keeps for it.

2024-Q12026-Q3

The timeline counts all 7 proposals here, since each one records the date it was first filed.

What kind of projects these are

The proposals naming this district, grouped by the sector each was filed under.

  • River Valley and Hydroelectric Projects 100%

The four largest sectors are shown by name and the rest are grouped as Other.

What is proposed here

These are the proposals in the national environmental clearance register whose application names a site in this district, newest first. A project with sites in several districts appears under each of them.

  1. Category AUnder Examination2026-09-28declares affected families

    Kurung Hydro Electric Project (292 MW)

    NORTH EASTERN ELECTRIC POWER CORPORATION LTD · River Valley and Hydroelectric Projects

  2. Category AADS Raised2026-04-17declares affected families

    NAYING HYDRO ELECTRIC PROJECT (1000 MW) - NEAR VILLAGE- YAPIK, DISTRICTS- SHI YOMI & SIANG, STATE- ARUNACHAL PRADESH

    NORTH EASTERN ELECTRIC POWER CORPORATION LTD · River Valley and Hydroelectric Projects

  3. Category AGranted2026-04-13declares affected families

    Etalin HEP 3097 MW

    NHPC LIMITED · River Valley and Hydroelectric Projects

  4. Category AEC Granted2025-07-17declares affected families

    Environment Clearance of Etalin HEP 3097 MW

    SJVN LIMITED · River Valley and Hydroelectric Projects

  5. Category AGranted2025-06-25declares affected families

    Environment Clearance of Etalin HEP 3097 MW

    SJVN LIMITED · River Valley and Hydroelectric Projects

  6. Category AToR Granted2024-05-11declares affected families

    NAYING HYDRO ELECTRIC PROJECT (1000 MW) - NEAR VILLAGE- YAPIK, DISTRICTS- SHI YOMI & SIANG, STATE- ARUNACHAL PRADESH

    NORTH EASTERN ELECTRIC POWER CORPORATION LTD · River Valley and Hydroelectric Projects

  7. Category AToR Granted2024-05-08declares affected families

    Kamala Hydro Electric Project

    NHPC LIMITED · River Valley and Hydroelectric Projects

All 7 proposals that name this district, newest first.