  1. 27 Oct 2026 · Details soughtEssential details soughtCapacity Expansion of Formaldehyde Manufacturing Unit in Existing Facility from 120 TPD to 200 TPD at…
  2. 24 Oct 2026 · ClosedDelisted automaticallyCapacity Expansion of Formaldehyde Manufacturing Unit in Existing Facility from 120 TPD to 200 TPD at…
  3. 19 Oct 2026 · Details soughtEssential details soughtCapacity Expansion of Formaldehyde Manufacturing Unit in Existing Facility from 120 TPD to 200 TPD at…
  4. 23 Sept 2026 · Details soughtEssential details suppliedProposed Expansion of Existing Formaldehyde Manufacturing Unit capacity from 40 MT/day to 160 MT/day…
  5. 16 Sept 2026 · Details soughtAdditional details soughtMining of Boulder ,Gravel and Sand in Toka Hamidpur Block over an area of 247 Acres In District Ambala…
  6. 4 Sept 2026 · ClosedDelisted automaticallyCapacity Expansion of Formaldehyde Manufacturing Unit in Existing Facility from 120 TPD to 200 TPD at…

Dated by the portal's own appraisal history, converted to India Standard Time; a proposal with no recorded history appears on its register submission date.

Other clearances these proposals declare

Forest land diversion declared
1
Forest land sought for diversion
Area not stated
Wildlife board recommendation declared
0
In or near a protected area
0
In an eco-sensitive zone
0

These counts are taken from the application forms of the 25 of 25 proposals naming this district whose forms have been read for these questions. In 11 of those forms at least one question was left blank, and a blank answer is counted as unknown. The forest area is the area stated for forest clearance, with each forest proposal counted once, in the district where its project is primarily sited.

Proposals naming this district
25
Category A proposals
14
Families declared displaced
150
Families declared affected
150

Displacement figures are the proponents’ own declarations. A project sited across several districts declares one figure for the whole project, and that figure is counted once, in the district where the project is primarily sited.

Fifth Schedule status

Not within a Fifth Schedule Scheduled Area

No Presidential Order under paragraph 6 of the Fifth Schedule declares any Scheduled Area in Haryana, so no part of this district is one and PESA does not apply.

OrderMinistry of Tribal Affairs, Scheduled Areas declared under paragraph 6 of the Fifth Schedule to the Constitution

What the record shows

  • Applicants for projects sited mainly in this district have declared 150 families to be displaced. The figure comes from their applications, and we have not verified it.

Each of these observations appears when a fixed rule is met by the figures on this page, so the same figures always give the same sentences. None of them is a view on whether a project should go ahead.

Who lives there

Figures from Census 2011, each compared with the all-India value computed on the same definition.

Total population
12,14,205
Households
2,35,423
Average household size
5.16
0.31 above India's 4.85India
Scheduled Tribe share of population
0.0%
8.6 points below IndiaIndia
Scheduled Caste share of population
25.3%
8.6 points above IndiaIndia
Children aged 0-6
12.1%
1.5 points below IndiaIndia
Literacy rate
78.0%
5.0 points above IndiaIndia
Sex ratio
878
65.1 below India's 942.6India

What they live on

How the district's workers earn a living, from Census 2011. The land-dependent share counts cultivators and agricultural labourers as a share of all workers, and it is the group most directly affected when land is acquired.

Total workers
3,89,233
Work participation rate
32.1%
7.7 points below IndiaIndia
Workers dependent on land
34.6%
19.9 points below IndiaIndia
Cultivators
15.8%
8.8 points below IndiaIndia
Agricultural labourers
18.8%
11.1 points below IndiaIndia
Marginal workers
12.9%
11.8 points below IndiaIndia
Household industry workers
3.2%
0.6 points below IndiaIndia

How households live

Land, income and work among rural households, from the Socio Economic and Caste Census 2011, which recorded these where the population census did not. Only the survey's rural part is used here, so urban households do not appear.

Rural households owning land
32.8%
13.3 points below IndiaIndia

The India figure is computed from 614 of 640 districts, because the source table has no value for the others.

Rural households whose highest earner makes over ₹5,000 a month
32.9%
8.6 points above IndiaIndia

The India figure is computed from 614 of 640 districts, because the source table has no value for the others.

Rural households living mainly on manual casual labour
57.6%
5.8 points above IndiaIndia

The India figure is computed from 614 of 640 districts, because the source table has no value for the others.

Rural households with a salaried member
9.4%
1.2 points above IndiaIndia

The India figure is computed from 614 of 640 districts, because the source table has no value for the others.

When these were filed

Each proposal is dated by the first step in its appraisal history, the dated record of steps the portal keeps for it.

2023-Q22026-Q3

The timeline counts 14 of the 25 proposals here. The first filing date comes from each proposal's appraisal history, and we have not yet read it for the other 11, so they are left out. Most of them are older proposals, so the early part of the timeline undercounts what was filed then. The register itself records a date for each of them; the gap is in our copy of the histories.

Hatched columns undercount, so they cannot be compared with solid ones. 2 of them cover periods for which we have read few filing dates so far, and they count only the proposals whose date we have.

What kind of projects these are

The proposals naming this district, grouped by the sector each was filed under.

  • Industrial Projects - 3 44%
  • Non-Coal Mining 40%
  • Thermal Projects 12%
  • INFRA-1 4%

The four largest sectors are shown by name and the rest are grouped as Other.

What is proposed here

These are the proposals in the national environmental clearance register whose application names a site in this district, newest first. A project with sites in several districts appears under each of them.

  1. Category AUnder Examination2026-09-23

    Proposed Expansion of Existing Formaldehyde Manufacturing Unit capacity from 40 MT/day to 160 MT/day located at Khasra no. 14/12/2, 12/3, 13/1/1, Village –Kunjal Jattan, Tehsil -Radaur, District- Yamuna Nagar, Haryana

    R S CHEMICALS · Industrial Projects - 3

  2. Category B1Referred to SEAC2026-07-25

    Mining of Boulder ,Gravel and Sand in Toka Hamidpur Block over an area of 247 Acres In District Ambala ,Haryana

    R. M. MINES AND INFRA PRIVATE LIMITED · Non-Coal Mining

  3. Category B2ADS Raised2026-06-25

    Proposed establishment of Resin Manufacturing Unit Within the Existing Plywood Manufacturing industry of M/s. Metro Plywood Pvt. Ltd.

    METRO PLYWOOD PRIVATE LIMITED · Industrial Projects - 3

  4. Category B1Standard ToR Granted2026-05-21

    Mining of Boulder ,Gravel and Sand in Toka Hamidpur Block over an area of 247 Acres In District Ambala ,Haryana

    R. M. MINES AND INFRA PRIVATE LIMITED · Non-Coal Mining

  5. Category AStandard ToR Granted2025-12-22

    Proposed Synthetic Resin Manufacturing Unit at Village Jathlana, District Yamunanagar, Haryana by M/s Royal Wood Industries.

    royal wood industries · Industrial Projects - 3

  6. Category AEC Granted2025-10-07

    Proposed Manufacturing Unit of Formaldehyde (120 TPD), Melamine Formaldehyde Resin of (30 TPD) and Urea Formaldehyde Resin (30 TPD) by M/s Adler Wood India Private Ltd.

    ADLER WOOD INDIA PRIVATE LIMITED · Industrial Projects - 3

  7. Category AProposal returned in present form2025-04-30

    Proposed manufacturing unit of Formaldehyde (120 TPD), Melamine Formaldehyde Resin (30 TPD) and Urea Formaldehyde Resin (30 TPD) by M/s Adler Wood India Pvt. Ltd.

    ADLER WOOD INDIA PRIVATE LIMITED · Industrial Projects - 3

  8. Category AEDS raised2025-04-03

    Capacity Expansion of Formaldehyde Manufacturing Unit in Existing Facility from 120 TPD to 200 TPD at village-jathlana, tehsil-radaur, jagadhri, Distt. YAMUNANAGAR, Haryana BY M/s Guruji Overseas

    M/S GURUJI OVERSEAS · Industrial Projects - 3

  9. Category AEC Granted2024-08-03

    Expansion of existing 2x300 MW coal based thermal unit by installing new 1x800 MW supercritical unit at Deen Bandhu Chhotu Ram Thermal Power Plant (DCRTPP), Yamuna Nagar, Haryana.

    HARYANA POWER GENERATION CORPORATION LIMITED · Thermal Projects

  10. Category AStandard ToR Granted2024-03-28

    Proposed Expansion of Existing Formaldehyde Manufacturing Unit capacity from 40 MT/day to 160 MT/day located at Khasra no. 14/12/2, 12/3, 13/1/1, Village –Kunjal Jattan, Tehsil -Radaur, District- Yamuna Nagar, Haryana

    R S CHEMICALS · Industrial Projects - 3

  11. Category B1Standard ToR Granted2024-01-11

    Boulder,Gravel and Sand Mining Project Jaidhari Block/YNR B 33 over an area of 48.60 Ha.

    KULWINDER SINGH · Non-Coal Mining

  12. Category AProposal returned in present form2023-12-08

    Expansion of Formaldehyde manufacturing unit in existing Facility from 100 TPD to 200 TPD at Village Bhagwanpur, Kharwan Road, Tehsil Jagadhri, District Yamuna Nagar, Haryana by M/s Chemwood Industries

    M/S CHEMWOOD INDUSTRIES · Industrial Projects - 3

  13. Category B1TOR GRANTED2023-09-06

    Expansion of Capacity for Boulder,Gravel and Sand mining project Malikpur Khadar Block/YNR B-28 having an area of 23.20 ha

    KARAJ SINGH · Non-Coal Mining

  14. Category AProposal returned in present form2023-08-29

    CAPACITY EXPANSION IN FORMALDEHYDE MANUFACTURING UNIT WITH THE EXISTING PRODUCTION CAPACITY 100 TPD TO 200 TPD AT VILLAGE BHAGWANPUR, KHARWAN ROAD, TEHSIL JAGADHRI, DISTRICT YAMUNA NAGAR, HARYANA BY M/S. CHEMWOOD INDUSTRIES

    M/S CHEMWOOD INDUSTRIES · Industrial Projects - 3

  15. Category B1EC Granted2023-07-06

    Mining of Boulder ,Gravel and Sand in Toka Hamidpur Block over an area of 247 Acres In District Ambala ,Haryana

    R. M. MINES AND INFRA PRIVATE LIMITED · Non-Coal Mining

  16. Category B1TOR GRANTED2023-06-30

    Boulder Gravel and Sand mining Project at Bailgarh North Block /YNR-1 in District Yamuna Nagar,Haryana Area 25.96 ha

    MANOJ KUMAR · Non-Coal Mining

  17. Category AToR Granted2023-06-06

    Expansion of existing 2x300 MW coal based thermal unit by installing new 1x800 MW supercritical unit at Deen Bandhu Chhotu Ram Thermal Power Plant (DCRTPP), Yamuna Nagar, Haryana.

    HARYANA POWER GENERATION CORPORATION LIMITED · Thermal Projects

  18. Category B1EC Granted2023-05-05

    Environment Clearance for expansion of Mining of Sand (Minor Mineral) from the Riverbed of Yamuna River in MT Karhera Block (YNR B-13) with 28,50,000 MT/ year production (Production increased from 21.0 Lacs to 28.5 Lacs TPA) over an area of 67.79 ha located at Village MT Karhera, Tehsil Radaur & District Yamuna Nagar and State Haryana

    KAWALJEET SINGH BATRA · Non-Coal Mining

  19. Category B1TOR GRANTED2023-03-10

    Mining of Boulder ,Gravel and Sand in Toka Hamidpur Block over an area of 247 Acres In District Ambala ,Haryana

    R. M. MINES AND INFRA PRIVATE LIMITED · Non-Coal Mining

  20. Category B1TOR Granted2023-03-01

    Environment Clearance for expansion of Mining of Sand (Minor Mineral) from the Riverbed of Yamuna River in MT Karhera Block (YNR B-13) with 28,50,000 MT/ year production (Production increased from 21.0 Lacs to 28.5 Lacs TPA) over an area of 67.79 ha located at Village MT Karhera, Tehsil Radaur & District Yamuna Nagar and State Haryana

    KAWALJEET SINGH BATRA · Non-Coal Mining

  21. Category ATOR GRANTED2023-02-27declares affected families

    Development of Industrial Estate (Phase-II)at Sector-30,30-A,31 & 32, Manakpur, Jagadhri, Haryana

    HARYANA STATE INDUSTRIAL AND INFRASTRUCTURE DEVELOPMENT CORPORATION LIMITED · INFRA-1

  22. Category B1TOR GRANTED2023-02-04

    Tajewala (BGS) Boulder, Gravel & Sand Minor Mineral, District- Yamunanagar, State- Haryana

    JAI MINING COMPANY · Non-Coal Mining

  23. Category ATOR GRANTED2023-02-02

    Expansion of existing 2x300 MW coal based thermal unit by installing new 1x800 MW supercritical unit at Deen Bandhu Chhotu Ram Thermal Power Plant (DCRTPP), Yamuna Nagar, Haryana.

    HARYANA POWER GENERATION CORPORATION LIMITED · Thermal Projects

  24. Category AEC Granted2022-11-15

    CAPACITY EXPANSION OF FORMALDEHYDE MANUFACTURING UNIT IN EXISTING FACILITY FROM 15 TPD TO 100 TPD KHASRA NO. 22//10, 11/2, 20/1/1, VILLAGE SHEZADPUR, TEHSIL JAGADHRI, DISTT. YAMUNANAGAR, BY M/S GOYAL OVERSEAS

    M/S GOYAL OVERSEAS · Industrial Projects - 3

  25. Category ATOR GRANTED2022-11-12

    Proposed manufacturing unit of Formaldehyde (120 TPD), Melamine Formaldehyde Resin (30 TPD) and Urea Formaldehyde Resin (30 TPD) by M/s Adler Wood India Pvt. Ltd.